Howard University Campus Plan

Howard University released this draft map to the public on March 31, 2011. Please note that this is not the final draft the university intends to submit for public review and to the Zoning Commission.

Loading…

New Construction & Renovation Timeline

    1-3 years: (Phase 1) 

  1. Science, Technology, Engineering, Mathematics (STEM) Building
  2. Computational Sciences & Retail
  3. Underclassmen Dorm #1 (??? beds)
  4. Underclassmen Dorm #2 (??? beds)
  5. 3-5 years: (Phase 2)

  6. Wellness, Recreation, Residences, Retail
  7. Blackburn Center Renovation
  8. School of Communications, Retail
  9. Support Services
  10. Nursing, Allied Health, Pharmacy Schools
  11. Nanotechnology Building
  12. Biomedical Engineering, Retail
  13. Upperclassmen Dorm #1, Retail
  14. Miner Building renovation
  15. 5-7 years: (Phase 3)

  16. Intercollegiate Athletics Complex
  17. Graduate/Workforce Housing
  18. Upperclassmen Dorm #2, Retail
  19. Teaching and Learning Building
  20. Future phase capacity:

  21. Academic/Athletic space
  22. Institutional Infill
  23. Middle School
  24. Academic/Research
  25. Academic/Research
  26. Academic/Research
  27. Academic/Research
  28. Academic/Research

Proposed Renovation Projects